Final approval and handover of a new-build flat: process and timelines
Final building approval and handover of a flat are two separate events. This article explains the sequence of steps, how to prepare for the handover inspection, what the handover protocol should contain and what to check in your contract.
Final building approval and the handover of a flat are two separate events. Final approval is an official decision that the building may be used for its intended purpose. Handover is a contractual step between you and the developer, at which you take over the flat, inspect it and sign a protocol. Usually the approval comes first and the handover follows, but the exact order and deadlines are set by your contract.
What final approval is and why it matters
Through final approval, the building authority confirms that the building was built according to the approved documentation and meets the conditions for use. The developer applies as the building owner. As a buyer you are usually not a party to the proceedings, but the outcome affects you directly: without a permit to use the building, you generally cannot legally move into the flat.
The authority may approve the building without reservations, approve it with conditions, or refuse approval until defects are removed. Minor defects that do not limit safe use are often resolved afterwards. More serious shortcomings can push the date back.
In practice the terms final approval, final approval consent and decision permitting use are used depending on which procedure applies to the particular building. What matters to you is that the developer should be able to show that the building may be used. Ask for a copy of the document.
The timeline from completion of construction to the keys
A typical sequence of steps looks like this:
- Completion of construction – finished structures, utility connections, common areas and the surroundings of the building.
- Application for permission to use the building – the developer submits the documentation, inspection reports and other documents to the authority.
- Inspection and decision by the authority – the authority may carry out an on-site inspection and issue a decision.
- Invitation to the flat handover – the developer invites you to take over the flat on a date set out in the contract.
- Handover inspection and protocol – inspection of the flat, recording of defects, handover of keys and meter readings.
- Removal of defects – the developer repairs the recorded defects within the agreed deadlines.
The length of each step varies with the size of the project and the workload of the authorities. Rely on the dates stated in your contract and in your communication with the developer, not on general estimates. You can follow the status of specific buildings in the project catalogue.
The handover inspection: how to prepare
Set aside plenty of time for the inspection, ideally in daylight. It helps to come with someone else, or to bring an independent construction technician who knows the typical defects of new builds.
What to check:
- that the layout, dimensions and fittings match the documentation and the contract,
- walls, ceilings and floors – evenness, cracks, damaged surfaces,
- windows and doors – seals, opening, locking, hardware,
- electrical installation – sockets, switches, circuit breakers, doorbell,
- water and drainage – pressure, tightness, outflow, function of taps and traps,
- heating, ventilation and, where fitted, cooling – function and controls,
- sanitary ceramics, wall tiles and floor tiles,
- balcony or terrace, cellar, parking space – whether they match the contract.
Have every defect entered in the protocol, even a minor one. Photograph it and record the exact location. What is not in the protocol is harder to prove later.
The handover protocol and defects
The protocol is the key document. It contains the condition of the flat, a list of defects, meter readings (water, electricity, heat, gas, where applicable), and the number of keys and documents handed over. Sign it only when it matches what you found during the inspection.
Check that each defect has a removal deadline. If not, ask for one to be added. The list of defects is not final: hidden defects that appear later can be claimed under the warranty. You will find the warranty terms and the complaints procedure in your contract, or you can discuss them with a lawyer.
Also ask how the developer will deal with the recorded defects and how they will inform you once the defects are removed. After a repair, it is advisable to inspect the flat again and confirm the repair in writing.
Payments, transfer of ownership and financing
The handover of a flat is often linked to financial steps: the final payment of the purchase price, release of funds from escrow or drawdown of a mortgage. Banks often have their own document requirements, for example a final approval document or the handover protocol. It is therefore wise to go through the procedure and timing in advance with a mortgage specialist.
Registration of ownership in the Cadastre of Real Estate may be separated in time from the handover. How it works in your case depends on the type of contract. Ask the developer or a lawyer when ownership passes, when you can start using the flat and when responsibility for the flat passes to you.
You can get a rough idea of monthly costs in the mortgage calculator. The specific terms will, however, be confirmed by the bank. General advice on the whole purchase process is in the buyer's guide.
What to check in the contract beforehand
- the expected date of completion and handover, including what happens in case of delay,
- a condition that the handover takes place after the permit to use the building is issued,
- the handover procedure and the deadlines for removing defects,
- the scope of the warranty and how to make a complaint,
- what is included in the price and what the final payment will be.
If you are still narrowing down your choice, compare the offers of developers and also consider the locations where you want to live. A non-binding housing inquiry form can help too.
Frequently asked questions
Can I refuse to take over a flat if it has defects?
It depends on how serious the defects are and on the contract. Minor defects are usually recorded in the protocol and removed afterwards. For serious defects that prevent use, consult a lawyer before you sign the protocol.
Must final approval be completed before the handover?
In general, the flat is expected to be handed over in a building that may be used. The exact conditions and the order of steps are, however, set by the contract, so have them explained to you before you sign.
Can I bring an expert to the handover?
Yes, and it is common. An independent construction technician can spot defects that a layperson easily overlooks. Agree the date with the developer in advance.
Prices are in Czech crowns (CZK) as published by developers; please verify current availability with us. Some linked pages (calculator, developer profiles) are only in Czech.
Find a new build within your budget
See the results right away, no contact details needed.
Looking for a new-build home in the Czech Republic?
Tell us what you are looking for. A specialist will send you a personal selection of projects within 24 hours, check current availability with the developer and arrange viewings. Free and without obligation.