Taking Over a New-Build Flat: A Step-by-Step Handover Checklist

Taking Over a New-Build Flat: A Step-by-Step Handover Checklist

11 October 2026
7 min read
Číst česky →

The best way to take over a new-build flat is to prepare in advance, inspect it room by room and have every defect recorded in the handover protocol. This article covers the preparation, the inspection itself and what happens afterwards.

You will manage the handover of a new-build flat best if you prepare for it in advance, go through the flat systematically room by room and have every defect you find written into the handover protocol. Signing the protocol is an important moment: do not let it contain anything you do not agree with, and do not sign under time pressure. This article guides you through the preparation, the inspection itself and what follows.

What the handover is and why it matters

The handover (taking over the flat) is the moment when the developer hands the finished unit to the buyer and the buyer confirms the condition in which they are accepting it. The result is a handover protocol, which describes the condition of the flat, meter readings, the keys handed over and a list of the defects and unfinished work found.

The protocol later serves as the main basis for complaints. Whatever you do not record in it will be harder to prove. It is therefore better to give the handover enough time and not to rush, even if the developer offers a short date. General information about the whole purchase process can be found in the guide to buying a new build.

Preparation before the handover

Good preparation saves a lot of trouble. We recommend these steps:

  1. Go through the contract and its annexes. Check what finish, materials and fittings were agreed. At the handover you compare the actual state against exactly these.
  2. Prepare the project documentation and the list of fittings. The floor plan of the flat and the specifications of floors, tiles, windows, doors and fixtures will come in handy.
  3. Set aside enough time. Allow several hours, ideally in daylight, so that the walls and floors are clearly visible.
  4. Consider an expert. A technician or construction supervisor will spot defects that a layperson can easily overlook. This may be a separate paid service; check the price with the specific company.
  5. Arrange the financial side. If you are financing the purchase with a mortgage, check with a mortgage specialist which documents the bank requires for drawing the loan and for the handover of the flat. You can calculate the approximate size of the instalments in the calculator.
  6. Bring the right tools. A tape measure, a spirit level or a smartphone with a level function, a strong torch, a plug-in socket tester, a camera and a notebook.

Checklist: what to go through in the flat

We recommend going through the rooms in a fixed order and taking a photograph of each defect, both a wider shot and a close-up. Here is an overview of what to focus on.

Entrance and doors

  • The entrance door opens and closes without sticking, the lock works, and the number of keys handed over matches the contract.
  • Door frames and doors inside the flat are not scratched or warped, they seal properly and do not rub against the floor.
  • The doorbell and the video entry phone or intercom work.

Walls, ceilings and floors

  • Plaster and paintwork are free of cracks, stains, bubbles and noticeable unevenness. Run your hand over the surface and look along the wall at an angle against the light.
  • Floors are level, do not sag and do not creak when you walk on them. Check the joints, threshold strips and skirting boards.
  • Floor tiles and wall tiles are intact, with no chipped edges and with even grout lines. Tapping will show whether any tiles sound hollow.
  • Silicone joints in the bathroom and kitchen are continuous and clean.

Windows and balcony or terrace

  • Windows open, tilt and close without problems, the fittings work and no seals are missing.
  • Glass is not scratched or cracked. Also check the window sills and blinds, if they are part of the delivery.
  • The balcony or terrace slopes correctly towards the drain, the railing is firm, and the waterproofing and paving show no visible damage.

Electrical installation

  • All switches, sockets and light points work and match the plan. Test the sockets with the tester.
  • The distribution board is clearly labelled and the circuit breaker can be switched on and off.
  • Check the data and aerial cabling, if it is part of the flat.

Water, drainage and heating

  • Hot and cold water run from the taps, the pressure is reasonable and nothing leaks. Run the water at all points at the same time.
  • Drains work well in the shower, washbasin, bath and sink. Flush the toilet and watch whether the cistern refills.
  • Radiators or underfloor heating warm up and the thermostats respond. Check that the valves do not drip.
  • Check the traps and connections under the washbasin and sink for water leaking.

Ventilation, meters and fittings

  • The fans in the bathroom and toilet extract air. The cooker hood and any heat recovery ventilation work.
  • Write down the readings of all meters (electricity, water, heat, gas) and check that the numbers match those in the protocol.
  • The kitchen unit, built-in appliances and sanitary ware (if included in the price) match the specification and are undamaged.
  • Inspect the cellar, parking space or garage as carefully as the flat, if they are part of the purchase.

How to record defects in the protocol

Have the defects you find described specifically: where they are, what they consist of and, ideally, with a reference to a photograph. General wording such as "minor defects" is unsuitable for enforcing a claim later.

  • For each defect, state the room and the location (for example "living room, north wall, crack above the window").
  • Ask for a deadline for remedying the defects and for the way in which you will be notified that they have been remedied.
  • Check that the protocol contains all the details: date, meter readings, number of keys, and representatives of both parties.
  • If you and the developer disagree, write into the protocol that you do not agree with a particular item.

A distinction is made between minor unfinished work and defects that prevent the flat from being used. Consult a lawyer on how to proceed in a specific case, especially if the defects are serious. Do not sign the acceptance if you are not sure that the protocol accurately describes the condition of the flat.

What follows after the handover

After the protocol is signed, the usual next steps are the remedying of defects, the handover of documents and keys, and the transfer of responsibility for the flat to you. Practical steps:

  • Keep track of deadlines. Write down the dates by which the developer is to remedy the defects, and check the defects again once they have passed.
  • Keep your documents. Store the protocol, photographs, warranty cards and instructions for the fittings in one place.
  • Handle complaints in writing. Report new defects that appear later to the developer in a verifiable way and keep a copy.
  • Register utilities and services. Transfer or conclude contracts for energy, water and internet, and use the recorded meter readings.
  • Arrange insurance. Take out property and household insurance so that it applies from the moment of handover.

If you are still choosing a flat and want to compare offers, in the project catalogue you will find new builds that you can filter, and you can browse them by area in the locations section. Information about builders is on the developers page. If you would like someone to prepare an offer for you, use the housing inquiry form.

Frequently asked questions

Can I refuse to take over the flat?

If the flat has serious defects that prevent its use, or does not match the contract, you can demand that they be remedied before you take it over. The procedure and consequences depend on the wording of the contract, so discuss it with a lawyer beforehand.

Should I bring a technician to the handover?

It is not mandatory, but an expert will uncover hidden and less visible shortcomings. Especially when buying a first flat, this investment often pays off. Check the price and scope of the service in advance.

What should I do if I discover defects only after moving in?

Report the defects to the developer in writing as soon as possible and attach photographs and a description. We recommend keeping confirmation of delivery. Consult a lawyer about further steps and deadlines.

Prices are in Czech crowns (CZK) as published by developers; please verify current availability with us. Some linked pages (calculator, developer profiles) are only in Czech.

Find a new build within your budget

See the results right away, no contact details needed.

Looking for a new-build home in the Czech Republic?

Tell us what you are looking for. A specialist will send you a personal selection of projects within 24 hours, check current availability with the developer and arrange viewings. Free and without obligation.

We need your phone number only for your request, our advisor will call you. We never pass it to developers automatically. We save your contact as you fill it in, so we can get back to you even if you do not finish the form.

By submitting you agree to the processing of personal data for the purpose of handling your request.

More articles